Enclosure Images: |
CMRR Project Phases:Radiological Laboratory/Utility/Office Building (RLUOB)
The RLUOB glovebox fabrication contract will comprise 19 open front boxes:The RLUOB glovebox fabrication contract will comprise 7 gloveboxes:All open front boxes and gloveboxes will require a surface treatment (coating) to improve the corrosion resistance of the enclosures. Ethylene-Chlorotrifluoroethylene (ECTFE) has been identified as the suitable coating material. Push-through gloveports are part of the CMRR design for enclosures. The RLUOB fabrication contract will encompass a total of 136 push-through gloveports. Double-door transfer systems (DDTSs) for sample transfer are part of the CMRR design for enclosures. The RLUOB fabrication contract will encompass a total of 9 push-through DDTSs. RLUOB Layouts
|